April 1, 2011 | Civilworx completed all demolition of structures, backfilling, compacting, and grading of the site. | March 10, 2011 | Second round of soil and groundwater injections scheduled to complete in-site chemical oxidation. | February 10, 2011 | First set of chemical oxidation injections scheduled to occur. | January 17, 2011 | Demolition of structures at 911 Allen Street and 100 E. 9th Street scheduled to begin. | January 10, 2011 | Asbestos abatement activities scheduled to begin. | January 3, 2011 | Demolition contractor Civilworx to begin mobilizing to the site | December 6, 2010 | Analysis of Brownfields Cleanup Alternatives released. | February 19, 2009 | City Hosts Brownfield Cleanup Project kick-off meeting | February 3, 2009 | Concurrent Technologies Corporation (CTC) selected as the City's Brownfield Consultant | November 23, 2008 | Request for Qualifications (RFQ) #2673 issued by the City for Brownfield Consulting Services | July 1, 2008 | City of Owensboro Awarded three EPA Brownfield Grants totaling $600,000 |
|
 |
|