June 2, 2011 | USTs used for storage of hydraulic fluid removed from former Pugh's Tire Service Center and post-removal sampling completed. |
June 1, 2011 | Eye-Integrated selected as firm to produce a video highlighting the City's brownfield's program following a competitive bidding process. |
April 1, 2011 | Additional assessment at Pugh's Tire Service is now underway. |
February 17, 2011 | Phase II ESA at the former Pugh's Tire Service Center completed. |
May 20, 2010 | Phase I ESA at the former Pugh's Tire Service Center completed. |
March 31, 2010 | Submitted a follow-up survey to property owners for the Warehouse District Multi-parcel Phase I ESA. |
March 31, 2010 | Finalized GIS redevelopment ranking maps for the West Greenville Redevelopment Area. |
March 5, 2010 | Held project team call. |
February 5, 2010 | Held project team call. |
February 1, 2010 | Developed presentation and held property owners meeting at City Hall to provide information on the Warehouse District Multi-parcel Phase I ESA. |
January 29, 2010 | Finalized the Phase I ESA Report and Asbestos & Lead-Based Paint Surveys for the Greenville Theatre Property. |
January 28, 2010 | Held project team call. |
January 15, 2010 | Submitted letters to property owners for 45 parcels in the Greenville City Center to notify them of plans for the Warehouse District Multi-parcel Phase I Environmental Site Assessment. |
January 6, 2010 | Held project team call. |
December 17, 2009 | Held a project team call. |
November 16, 2009 | Attended the EPA National Brownfields Conference in New Orleans, LA. |
November 14, 2009 | Finalized the Phase I ESA Update for the Imperial Tobacco site. |
November 11, 2009 | Finalized the Phase I ESA Report for the SW Redevelopment site. |
October 9, 2009 | Conducted the Phase I ESA site visit at the SW Redevelopment site. |
October 6, 2009 | Finalized the revised Phase II ESA Report for the Imperial Tobacco site. |
September 30, 2009 | Held a project team call. |
September 15, 2009 | Held a project team meeting. |
September 15, 2009 | Met with EPA Project personnel. |
September 15, 2009 | Met with the prospective developer of the Imperial Tobacco site. |
September 15, 2009 | Met with the property owner of the Greenville Produce property. |
September 7, 2009 | Conducted the lead-based paint and asbestos surveys at the former Greenville Theatre property. |
September 4, 2009 | Held a project team call. |
August 25, 2009 | Conducted the Phase I ESA site visit at the former Greenville Theatre property. |
August 25, 2009 | Conducted the Phase I ESA update site visit at the Imperial Tobacco site. |
August 21, 2009 | Finalized the Phase I ESA at the Greenville Produce property. |
June 17, 2009 | Finalized the GIS Site Inventory for the West Greenville Redevelopment Area. |
May 12, 2009 | Held a developers' roundtable luncheon. |
May 12, 2009 | Held the West Greenville Redevelopment Area brownfields urban planning and design meeting. |
May 8, 2009 | Held project team calls. |
May 7, 2009 | Initiated Phase I ESA activities at the Greenville Produce, former Greenville Theatre, and Imperial Tobacco properties. |
April 23, 2009 | Held project team calls. |
April 23, 2009 | Finalized Public Involvement Plan and outreach materials. |
February 9, 2009 | Met with prospective purchaser of the Imperial Tobacco site. |
February 9, 2009 | Conducted a project team meeting. |
February 9, 2009 | Initiated visioning activities for the Imperial Tobacco site and surrounding properties. |
January 7, 2009 | Met with prospective purchaser of the Imperial Tobacco site. |
December 9, 2008 | Held project team conference call to update on progress. |
October 29, 2008 | Held project team conference call. |
October 8, 2008 | Held brownfields stakeholder meeting. |
October 7, 2008 | Held brownfields kick-off meeting. |
October 3, 2008 | Held conference call with project team to discuss scope of land planning work. |
September 22, 2008 | Received and evaluated four (4) responses to the Urban Planning and Design RFP. |
September 22, 2008 | Selected Land Design to complete urban planning/design/visioning for the Imperial Tobacco site and immediate surrounding area. |
September 18, 2008 | Held conference call to discuss Land Planning RFP. |
August 22, 2008 | Identified an additional four (4) planning and design firms and resubmitted the Urban Planning and Design RFP with a due date of September 12, 2008. |
August 22, 2008 | Held project team conference call to discuss Land Planning RFP. |
July 22, 2008 | Finalized Urban Planning and Design Request for Proposal (RFP) for the Imperial Tobacco site and immediate surrounding area and submitted to five (5) planning and design firms with a due date of August 8, 2008. |
June 23, 2008 | A Phase II ESA was completed at the Imperial Tobacco site. |
June 23, 2008 | Held a project team call to discuss the Urban Planning and Design RFP. |
May 30, 2008 | A Phase I Environmental Site Assessment (ESA) was completed at the Imperial Tobacco site. |
May 5, 2008 | One (1) City staff member attended the Environmental Protection Agency (EPA) National Brownfields Conference in Detroit, MI. |
April 3, 2008 | Outlined brownfield program goals, plans, and activities at the Chamber of Commerce Business Expo. |
March 13, 2008 | Selected team of Concurrent Technologies Corporation (CTC) and Dunklee and Dunham to provide environmental services. |
February 27, 2008 | Selected five (5) environmental consulting firms for interviews. |
January 18, 2008 | Received and evaluated seven (7) proposals from environmental consulting firms in response to the Request for Qualifications (RFQ) to provide assistance to the City in completing the brownfield project activities. |
December 18, 2007 | Prepared and issued a Request for Qualifications (RFQ) for environmental consulting firms to provide assistance in completing the brownfield project activities. |
July 24, 2007 | Two (2) City personnel attended the Environmental Protection Agency (EPA) Region 4 Grantees Workshop in Charleston, SC. |