September 29, 2011 | The City finalized Phase II ESA Report for Plummer Properties |
September 15, 2011 | The City held Project Team call |
September 13, 2011 | The City finalized TBA applications for 800 Taylor Street, 200 E. Umstead (Whitted School) property, and Durham Central Market property |
August 24, 2011 | The City attended IEDC Training – Neighborhood Development Strategies in Oklahoma City, OK |
August 19, 2011 | The City held a Project Team call |
August 16, 2011 | The City finalized Vapor Intrusion Study Report for 102 Morris Street |
August 1, 2011 | The City finalized Limited Site Assessment Report for 1901 Angier Avenue |
July 29, 2011 | The City finalized Phase II ESA Report for 102 Morris Street |
June 16, 2011 | The City participated in EPA Debriefing Webinar on the FY2011 EPA Brownfield Applications |
June 1, 2011 | The City announced plans for and solicited support for the Environmental Awareness High School Event to Small Business Advisory Committee, Inter-PAC Environmental Justice Committee |
May 26, 2011 | The City planned and facilitated a brownfields Task Force Meeting |
May 13, 2011 | The City finalized the Phase II ESA Report for 1901 Angier Avenue |
April 27, 2011 | The City submitted the Site Specific QAPP to the EPA and NCDENR for review for 800 Taylor Street Property |
April 11, 2011 | The City received the signed property owner memorandum of understanding from Durham County for Whitted School property |
April 2, 2011 | The City attended the EPA National Brownfields Conference in Philadelphia, PA |
March 25, 2011 | The City received approval from EPA Region IV on the Site Specific QAPP for 102 Morris Street property |
March 24, 2011 | The City promoted the Brownfields Assessment Project goals, and accomplishments during a presentation to the City Council Work Session |
March 2, 2011 | The City participated in the Career Fair and Green Trade Show |
February 22, 2011 | The City attended a "Scientifica" research workshop designed for high school students in the Durham Public Schools |
February 19, 2011 | The City discussed the Brownfields Assessment Project to the economic development of NECD District PAC 1 during their "Coffee with Council" meeting |
February 18, 2011 | The City submitted the Site-Specific QAPP for 102 Morris Street property to EPA Project Manager for review |
February 16, 2011 | The City initiated the Phase II ESA field work at 1901 Angier Avenue property |
February 14, 2011 | The City conducted a presentation to the Northeast Central Durham Livability Sustainability Initiative |
January 29, 2011 | The City received approval from EPA Region IV on Site Specific QAPP for Plummer Properties |
January 28, 2011 | The City finalized the Phase I ESA Report for Durham Central Market Property |
January 21, 2011 | The City completed additional asbestos inspection activities at 102 Morris Street property and provided report to property owner |
December 20, 2010 | The City finalized the Phase I ESA Report and HUD Assessment at 727 N. Mangum Street. |
December 15, 2010 | The City finalized the Site-Specific QAPPs for 1901 Angier Avenue and Tucker Properties |
November 30, 2010 | The City participated in a Public Information Session at Eastway Elementary School. |
November 18, 2010 | The City participated in the Brownfields Assessment Project's Presentation to the Durham City Council. |
November 18, 2010 | The City attended the Council Subcommittee on Northeast Cental Durham. |
October 29, 2010 | The City Finalized the Site Specific QAPPs for properties located at 1901 Angier Avenue, Tucker Properties, and Plummer Properties, |
October 14, 2010 | The City participated in the People's Garden School Pilot Prospective Application Webinar session |
October 7, 2010 | The City promoted the Brownfields Assessment Project at the Minority Enterprise Development Trade Fair at the Durham Convention Center. |
September 28, 2010 | Gave a project presentation to approximately 40 community members of the Northeast Central Durham (NECD) Livability Initiative meeting |
September 15, 2010 | Provided updates of the Brownfields Assessment Project to the Northeast Central Durham (NECD) Leadership Council |
September 15, 2010 | Gave a project presentation to approximately 100 members of the Environmental Health Collaborative Organization during the Environmental Health Summit. |
August 15, 2010 | Provided updates of the Brownfields Assessment Project to the Northeast Central Durham (NECD) Leadership Council |
August 15, 2010 | Completed Phase I Environmental Site Assessment Report for 800 Taylor Street |
August 15, 2010 | Completed Phase I Environmental Site Assessment Report for 200 E. Umstead Street |
August 10, 2010 | Gave a project presentation to 19 members of the Campaign for Decent Housing community group |
July 21, 2010 | Attended EPA Region 4 Grantee Workshop in Jacksonville, Florida |
July 16, 2010 | Completed and submitted Property Owner Access Agreements for 502 N. Roxboro Street and 102 Morris Street |
July 15, 2010 | Finalized Public Involvement Plan |
July 15, 2010 | Provided updates of the Brownfields Assessment Project to the Northeast Central Durham (NECD) Leadership Council |
July 15, 2010 | Selected Dominion Due Diligence Group to complete Phase I ESA at 502 N. Roxboro Street |
July 15, 2010 | Planned Kickoff for October 7th, to be held during the Minority Economic Development Week Trade Fair from 4-6:30 pm at the Durham Convention Center. The theme is How a Brownfields Site Assessment can Jumpstart Business in Your Neighborhood! |
July 10, 2010 | Gave a project presentation to 35 members of the Partners Against Crime District 4 community group |
June 15, 2010 | Held Brownfields Task Force Meeting |
June 15, 2010 | Conducted tour of potential brownfields sites with the EPA Project Manager |
June 11, 2010 | Completed and submitted Property Owner Access Agreements for 200 East Umstead Street and 727 North Mangum Street |
May 5, 2010 | Completed and submitted Property Owner Access Agreements for 800 Taylor Street, 832 Ridgeway Avenue, 1901 Angier Avenue, Tucker Properties, and Plummer Properties |
April 16, 2010 | Received approval from the EPA Designated Approval Official for the Generic Quality Assurance Project Plan (QAPP) |
April 6, 2010 | Completed the 1901 Angier Avenue Phase I Environmental Site Assessment |
February 23, 2010 | Issued a notice to proceed/purchase order to Porter Scientific for the 1901 Angier Avenue Phase I Environmental Site Assessment |
February 18, 2010 | Finalized and submitted Generic Quality Assurance Project Plan (QAPP) to EPA for review |
November 17, 2009 | Attended EPA National Brownfields Conference in New Orleans, LA |
September 30, 2009 | Completed Phase I ESAs at Plummer and Tucker Properties |
September 16, 2009 | Completed Phase II ESA field activities at the 812 Liberty Street property |
June 30, 2009 | City hosts fifth Brownfields Task Force meeting |
June 30, 2009 | City held a Vision to Action Workshop |
December 23, 2008 | Finalized the Phase I ESA for the Liberty Street Property |
December 10, 2008 | Brownfields Job Training Grant Advisory Committee Meeting |
October 21, 2008 | City hosts fourth Brownfields Task Force meeting |
October 21, 2008 | City holds public meeting to discuss submittal of another EPA Brownfields Assessment Grant Application |
September 20, 2008 | Completed Phase II ESA and Report for Angier Property |
September 1, 2008 | Completed Phase I ESAs at Liberty Street and Plum Street Properties - draft reports |
July 22, 2008 | CTC and Porter Scientific initiate Phase I Environmental Site Assessment at properties on Liberty Street and Plum Avenue |
July 22, 2008 | CTC and Porter Scientific initiate Phase II Environmental Site Assessment at property on Angier Avenue |
July 7, 2008 | Received approval from Region IV EPA regarding Phase II Environmental Site Assessment Work Plan for property on Angier Avenue |
May 27, 2008 | City hosts second Brownfields Task Force meeting. |
May 5, 2008 | City delegates attend National Environmental Protection Agency Brownfields Conference in Detroit, Michigan |
April 24, 2008 | Project Team presents project updates at City Council Workshop. |
April 17, 2008 | Submitted Work Plan for Phase II Environmental Site Assessment at property on Angier Avenue to Region IV EPA for their review. |
February 12, 2008 | Project Team completes a summary of community outreach activities from November 2007 to February 2008 |
February 7, 2008 | CTC and Porter Scientific initiate Phase I Environmental Site Assessment at property along East Pettigrew Street |
February 5, 2008 | City hosts first Brownfields Task Force Meeting |
November 15, 2007 | City finalizes Project Public Involvement Plan |
November 15, 2007 | City finalizes Project Brochure |
October 25, 2007 | City holds Public Information Session to "kick-off" project |
June 17, 2007 | City signs contract with CTC to manage grant |
December 28, 2006 | City issues Request for Proposals to qualified consultants for assistance in managing the assessment grant |
July 11, 2006 | City delegates attend Region 4 EPA New Grantees Workshop, Atlanta, Georgia |
June 30, 2006 | City submits Project Work Plan to EPA |
May 12, 2006 | The City is selected by the EPA to receive the brownfield grant |